CONCEPT PLAN

November 11, 2007

Approved by Planning Commission

January 23, 2008

Approved by Metro Council

January 23, 2011

Expiration Date to submit Final Development Plan

FINAL DEVELOPMENT PLAN (PHASE 1)

September 22, 2008

Approved by Planning Commission

September 22, 2010

Expiration Date

September 22, 2009

Another Final Development Plan for an undeveloped Phase must be submitted within 12 months of the approval of the Final Development Plan for Phase 1.

FINAL DEVELOPMENT PLAN (PHASE 1B) LIBRARY

September 21, 2009

Submitted Plan

November 9, 2009

Approved by the Planning Commission

November 9, 2011

Expiration Date

November 10, 2009

MC Introduction to appeal failed

FINAL DEVELOPMENT PLAN (PHASE 4A) Apartments

September 22, 2009

Submitted Plan

November 9, 2009

Approved by the Planning Commission

November 9, 2011

Expiration Date

November 10, 2009

MC Introduction to appeal failed

May 17, 2010

The vision of Rouzan is coming to fruition with the launch of The Mimosa District, the first opportunity for home site ownership within the TND. Groundbreaking is anticipated within the next 90 days.